Urinal Installation Process

1. Preparation

  • Check wall height and mark centreline and bottom level of urinal.
  • Ideal height (centre of bowl):
    • Adults: 610–650 mm (24–26 in) from floor
    • Children: 450–500 mm

2.Bracket Fixing

  • Mark the bracket/hanger bolt positions on the wall.
  • Drill holes and fix with wall plugs and screws or bolts.
  • Brackets must be level and firmly secured.

3. Water Supply Connection

  • Install flush valve or sensor system at recommended height (around 100–150 mm above urinal).
  • Connect it to the water inlet pipe using PTFE tape and wrench.

4. Waste Outlet Setup

  • Ensure the waste pipe (PVC or CPVC) is at correct height and slope.
  • Use appropriate trap (bottle trap or P-trap) connected to drainage.
  • Apply PVC solvent cement at joints.

5. Urinal Mounting

  • Hang or fix the urinal onto the brackets or hanger bolts.
  • Ensure it fits flush against the wall and aligns with the waste pipe.

6. Sealing & Testing

  • Apply silicone sealant around the edges.
  • Turn on the water supply.
  • Test flush, check for leaks at:
    • Inlet connection
    • Flush valve
    • Outlet pipe